
One of the most important milestones in the electricity interconnection project of Crete-Attica, the laying and installation of all the 500 kV direct current technology submarine cables, was successfully completed in the previous days by Independent Power Transmission Operator-IPTO’s subsidiary company Ariadnie Interconnection.
As highlighted, within 32 months of the signing of the contracts for the large energy project, in June 2020, Ariadne Interconnection laid a total of approximately 1,350 km of electric cables and optical fiber cables between Korakia, Heraklion and Pachi Megara. The depth of the installation at the bottom of the Aegean reached up to 1,200 meters from the sea surface, while the weight of the cables exceeds 40 kg per meter.

With the completion of the cable protection works, expected in the second quarter of 2023, 640 km will have been laid below the seabed surface for maximum safety.
The casting of the electrical cable sections was carried out in stages from the end of 2021 to the beginning of 2023, in the context of three different operations by the two contracting companies of the project.
For these operations, which had particularly high technical requirements, a total of five specialized cable work vessels were used, including the two most modern cable laying vessels in the world, Aurora and Leonardo da Vinci.
For the successful laying of the submarine cables, from October 2020 to May 2021, a thorough seabed study by the contracting companies Prysmian and Nexans was preceded, and the optimal routing and protection of the cables was planned with both technical and environmental criteria.
The electrical interconnection of Crete with Attica is the largest energy investment, amounting to 1 billion euros, currently being carried out in the country, with which IPTO will fully integrate Crete into the continental electricity transmission system, by the end of 2024.


Latest News

Greece, Hellenism celebrate 202nd anniversary of 1821 independence struggle
Greece and ethnic Greek communities around the world on Saturday celebrated the nation’s annual March 25 Independence Day

Intrakat eyes acquisition of Ellaktor subsidiary Aktor in deal worth roughly 200mln€
All three of the companies are among the top construction companies, developers and infrastructure concessionaires in the country

Travel receipts up by 72% in Jan. 2023
The balance of travel services in January 2023 showed a surplus of 26.3 million euros, down from a surplus of 44.0 million euros in January 2022

Bilateral work group tasked with considering revival of plan for Burgas-Alexandroupolis pipeline
The meeting was attended by each country’s energy minister, Kostas Skrekas and Rossen Hristov, respectively

US President Biden proclaims Greek Independence Day as a national day of celebration of Greek, American democracy
Inspired by Greece's War of Independence in 1821, Biden referred in his message to the historically high level of Greek-American relations

PPC announces higher operating earnings, lower debt; EBITDA up 9.4% from 2021
Public Power Corp. (PPC) SA on Thursday reported higher operating earnings

Bloomberg op-ed piece: Greece’s recovery ratified in its low cost of borrowing; below average for investment-grade borrowers anywhere
A high-profile opinion piece by Bloomberg

Amendment suspends building activity on Mykonos in areas outside town planning zones, following last week’s assault on archaeologist
Additionally, and even more importantly, an amendment passed in Parliament on Tuesday suspends all building activity on Mykonos in areas outside of town planning (zoning) areas

Titan cement group reports 33.1-percent increase in 2022 sales
Titan Group reported a 33.1-percent increase in 2022 sales, reaching 2.282 billion euros

Renewable energy source power production in Greece exceeds 10GW in early 2023
Power production from renewable energy sources in Greece exceeded the 10GW-threshold in early 2023