A thirty-year cycle is closing, while a new one has already opened with the Athens metro adding an additional 38.3 km to the 85.3 km existing network.
Today, more than 2.6 million Athenians have access to rail transport, a number that will grow in the next decade, but there is still a long way to go. With the additional 15 stations of the new Line 4, it will have just one station per square kilometer, when Paris has four.
Read also: Athens Railway Station in second phase of renovation
Transport hub
Athenians’ favorite transport is turning a page next fall. At the end of September, the three remaining stations of the extension to Piraeus, in Maniatika, Piraeus, Municipal Theater, are expected to be open to passengers.
Early testing is going well and the final steps are progressing on schedule. The new stations are estimated to add 69,000 passengers to the network daily.
Piraeus will become the largest transport and logistics hub in the country, centered on the port, as commuters will be able to get to Athens International Airport within 50 minutes, featuring connections to Lines 1 and 3 of the metro, as well as to the suburban railway, through which it will also link with the railway.
Countdown
With studies going full steam, building the foundations of the huge 12.8 km project of the new “Alsos Veikou – Goudi” line, this autumn the capital , 28 years after the arrival of the first TBM machine, will welcome two brand new “moles”. Thus in early 2023, the countdown will begin for the start of work on the largest infrastructure project currently underway in Europe, worth 1.8 billion euros.
The two state-of-the-art, silent boring machines will start the underground journey from both ends of the new orange line. At that time, the first tunnel boring machine is being dismantled to arrive from Germany through the port of Piraeus in September, so that it can be reassembled and “burrow” in Katehaki Avenue.
While the second TBM that will arrive in October will start from Alsos Veikou park, so that the two machines will meet at “Evangelismos”, essentially digging the two “arms” of the new line which has a “U” shape ».
Network shifts
As for the preparatory works of the project, construction sites have already been activated in 13 of the 15 stations. On July 31, in fact, the relocation of utility networks began at the “Kolonaki” station in Filiki Etairias square (archaeological work is already being carried out at the construction site), for which traffic arrangements are required, with the first phase lasting approximately 3 weeks.
The most difficult task, as expected from the beginning, is the construction site in Exarchia Square.
Attiko Metro’s attempts to launch work without police presence to date have failed, so the next step will be taken directly under the umbrella of police forces. Besides, as the Ministry of Infrastructure has made clear, the design of the project, delivered by the previous government, is not going to change.
The “Evangelismos” station developed also brought about reactions, with the Rizari park at the forefront, where the way to improve the design is being studied, but within the provisions of the existing environmental permit.
The expansions that will decongest Attica Basin
Amidst the financial crisis, only the extension of Line 3 to Piraeus began in Athens, with the accumulated financial and engineering problems leading to the delivery of the entire project with a delay of 5 years (the first three stations were put into commercial operation in July 2020). But a new generation of expansions is coming to the fore, as the priority of the Ministry of Infrastructure and Transport is to “run” pro-environmental projects that will relieve the worsening traffic congestion in the Basin.
ANTHOUPOLI – ILION:
The first step is to launch the tender for the 4.1 km longextension of Line 2, in the Anthoupolis – Ilion section, with three stations in Palatiani, Ilion and Agios Nikolaos, with an estimated budget of 350 million euros, within the autumn.
It is estimated that it will serve 50,000 passengers a day, significantly reducing the time currently required to reach the city center. In the next phase, it is planned to further extend the line with three stations to Kamatero and Ano Liosia, where it will be connected to the suburban railway on Attiki Odos, finally ending in Acharnes (center of Menidi).
STAVROS NIARCHOS FOUNDATION:
The metro is also setting off for the Stavros Niarchos Foundation Cultural Center in Kallithea, and from there to Ilioupoli, Glyfada and Petroupoli. A bunch of new extensions, which are expected to add about 22 km and 17 new stations to the network and are being gradually designed by Attiko Metro.
The priority is the underground connection of the 5 km long electric line after the Thisio station to Kallithea, with four stations: Hamosternas, Davaki Square, Filaretou Hill/Tzitzifies and Stavros Niarchos. The cost is estimated at 450 million euros. The next phase of the line’s development will extend towards Paleo Faliro, along Amphithea Avenue.
ELLINIKO – ANO GLYFADA:
The 4.4 km long “southern” extension of Line 2 from Elliniko, with stations at Ano Glyfada, Vouliagmenis Avenue and Glyfada, is still being prepared, with a budget of 350 million euros. While two extensions of the new Line 4 are in the pipeline.
These are the sections “Evangelismos – Ano Ilioupoli”, 4.1 km long with three stations, and “Alsos Veikou – Petroupoli”, 7.5 km long with six stations in Nea Ionia, Pefkakia (correspondence with Line 1), Nea Philadelphia, Agioi Anargyroi (Pyrgos Vasilissis), Ilion and Petroupoli. The total budget of the two projects is estimated at close to 1 billion euros.
GOUDI-MAROUSI:
In the foreground is the development of the extension from Goudi to Marousi with seven new stations that will serve the municipalities of Psychiko-Filothei, Chalandri and M arousi and then with three stations to the Athens – Thessaloniki National Highway.
The twin project has an estimated budget of over €1 billion. The next stage of development of Line 1, after the KAT station to Kifissia, N. Erythraia and the Varymombi junction, also aims at connecting the network with the National Highway. The continuation certainly requires funds which will be sought in the future.
Latest News
Greek Retailers Remain Optimistic About Easter Shoppers’ Turnout
While stores are expected to be open on Sunday, April 28, the majority of Easter shoppers will likely do their shopping during the Holy Week, following the deposit of Easter bonuses
Europeche: Greek Apricot Production Recovers
Europeche forecasts the production will bounce back despite a slight decrease in varieties attributed to high winter temperatures
Bank of Greece (BoG): Business-Household Deposits Up 1,675bln in March 2024
In March 2024, the monthly net flow of credit to the general government was negative by 469 million euros
FT: Greece’s Economic Rebound a Balance of Growth and Poverty
Eurostat data revealed a significant 10.8% drop in Greek public debt relative to GDP in 2023, alongside a 2% economic expansion, outpacing Germany's performance.
Lavrio Port Authority Next Up for Privatization
A deadline for the submission of expressions of interest is May 14, 2024
Eurostat: Greece Records Largest Drop in Natural Gas Prices in 2nd Half of 2023
The price of electricity and natural gas in Europe was down following a substantial surge that began before the Russian invasion of Ukraine and peaked in 2022
GEK TERNA Still Considers Leveraging Concessions Portfolio as Financial Tool
President and CEO of Gek Terna George Peristeris explained the company's plans on Tuesday on the sidelines of the inauguration of sections of Greece's E65 highway
NielsenIQ: 3% Supermarket Revenue Increase in Q1
Private label products are gaining traction, comprising 25.4% of shopping basket shares, up from 24.7%
Store Hours Change Today in Observation of Orthodox Easter
The President of the Athens Chamber of Commerce hopes the Easter period will provide a much-needed boost to retail traffic in the capital
Athens-area Mass Transit Systems Set to Finally Install Contact-less Fare Payment
Paying fares via bank cards, smartphones and smartwatches in all mass transit systems in the Greek capital, namely, buses, trolleys, the metro and tram lines, is scheduled by the end of the year